Skip to main content

10.2 Office Holidays tab

Use this tab for public holidays and other closures.

Figure 10.3 The Office Holidays tab
  1. Tick Are you closed for holidays?.
  2. Click + Single Day for a one-day closure, or + Date Range for several days.
  3. Enter the Holiday Name (for example Shutdown) and choose the month and date. For a range, set From - Month, From - Date, To - Month and To - Date (for example 29 October to 4 November).
  4. Repeat for each holiday. Click the bin icon to remove one.
  5. Click Save.